Sites and Structures Report, January 2020
Sites & Structures Committee Report to the Board of Directors, January 7, 2020 George Douglass House Restoration Project, Summary of Work Accomplished October 1, 2019 to December 31, 2019: During this quarter substantial progress was achieved in first floor parlors, kitchen, and Amity Store room in the categories of interior plasterwork, jo