#1: Deteriorated and missing plaster along chair rail in store room
Documents 1008.01.085

Sites and Structures Report GDH, June 30, 2019

Sites and Structures Reports · June 30, 2019

SITES AND STRUCTURES REPORT GDH JUNE 30, 2019 Description: WORK PROGRESS SINCE APRIL 1, 2019: I. CARPENTRY AND JOINERY: Front (NW) parlor: The majority of the floor boards in the best parlor required substantially more shop-work and on-site carpentry and joinery to conserve, functionally restore, re-nail, and level in their historic locations as

View record
#1: Plaster scratch coat keyed into partition lath in kitchen
Documents 1008.01.086

Sites and Structures Report GDH, September 30, 2019

Sites and Structures Reports · September 30, 2019

I. PLASTERWORK: Interior: During the 3d quarter of 2019, the project plasterer, William Smith of Brandywine Historic Services, made substantial progress in the interior work, including restoration of wall and ceiling integrity in the 1st floor kitchen. Specific accomplishments include: (A) Determining which original 1765 plaster ranges are soundly ancho

View record
#1: 1765 plaster fragment with hair binder
Documents 1008.01.083

Sites and Structures Report-GDH, December 31, 2018

Sites and Structures Reports · December 31, 2018

George Douglass House Project work Accomplished October 1, 2018 to December 31, 2018 Continuing plasterwork begun in the 3d quarter of 2018, the following significant progress was made on exterior plaster restoration on the cove cornices on the façade and north gable-end, and with interior plastering in the 2d floor chambers: Exterior cove cornices:

View record
#1: Preserved original [left] and new [right] plasterwork
Documents 1008.01.084

Sites and Structures Report-GDH, March 31, 2019

Sites and Structures Reports · March 31, 2019

George Douglass House Project work Accomplished January 1, 2019 to March 31, 2019 During the 1st quarter of 2019, our project plasterer (working on his 20th National Register structure) made substantial progress in the interior work, restoring wall integrity and surface finishes in the 2d floor chambers and hallway. This work progressed with the sensiti