George Douglass House Restoration Report for the quarter ending September 30, 2018
George Douglass House Restoration Accomplishments, July 1 to September 30, 2018 During the 3d quarter of 2018, the primary restoration focus has been devoted to: A. Exterior: Restoring the plastered cove cornice on the primary façade; photo #19 shows a run of the cornice on the primary façade before restoration, with missing and damaged plaster and lath.