Series of 19 images showing perspective views of the Keim House and other dwellings, detail views depicting evidence of an early plastered cove cornice on the Keim house, and other related photos, including images of houses built during the same quarter-century period as the Keim house and earlier English antecedents displaying plastered cove cornices. I

View record
#1, 2458: "Spanish Brown" 2d coat on shutter and cellar doors
Documents 1008.01.072

Sites and Structures Report December 2014

Sites and Structures Reports · December 2014

Sites & Structures Report, Dec 2014 This report will focus on the following projects and issues to be discussed and resolved: 1. Paint Problems: The Benjamin Moore paint stores have been unable to match some of the historic colors determined by Matt Mosca from specimens taken from the early woodwork elements. The resulting off-color paints which have

View record
Image #1: chipped "keys" in base plaster; replaced lath and chair rail
Documents 1008.01.088

Sites and Structures Report GDH, June 30, 2020

Sites and Structures Reports · June 30, 2020

Work Progress during this 2d quarter period: interior plastering and woodwork joinery continued intermittently as weather, planning details, coordination between crafts, and Pandemic restrictions permitted. Our carpenters Tom & Chris Lainhoff continued to fabricate parlor elements such as wainscot paneling under windows [see Image #12], and best parlor wains

View record
#1: 1765 plaster fragment with hair binder
Documents 1008.01.083

Sites and Structures Report-GDH, December 31, 2018

Sites and Structures Reports · December 31, 2018

George Douglass House Project work Accomplished October 1, 2018 to December 31, 2018 Continuing plasterwork begun in the 3d quarter of 2018, the following significant progress was made on exterior plaster restoration on the cove cornices on the façade and north gable-end, and with interior plastering in the 2d floor chambers: Exterior cove cornices: